Zesco commission 330KV line for Northern and Eastern provinces

Share

Zesco Limited Managing Director Cyprian Chitundu delivers a speech during the launch of the 330 KV power line transmission Kasama yesterday
Zesco Limited Managing Director Cyprian Chitundu delivers a speech during the launch of the 330 KV power line transmission Kasama yesterday

THE construction of the US $334 million ZESCO 330 kv high voltage transmission lines will create over 3000 direct and indirect jobs in Eastern, Luapula, Northern and Muchinga Provinces, among other benefits, Chinese Ambassador to Zambia Zhou Yuxiao has said.

This came to light when Mines, Energy and Water Development Minister Christopher Yaluma officiated at the groundbreaking ceremony of the project in Kasama yesterday.

Mr Yaluma said once completed the frequent power outages at peak hours the four provinces had been experiencing for a long time owing to the inadequate 66 kv power they were receiving from Pensulo substation would be a thing of the past.

Mr Yaluma observed that electricity was no longer a luxury, but a necessity which was useful in driving industrial development and promoted overall economic growth besides it improving the lives and social development of the citizenry thus pledging Government’s commitment to ensuring that a larger portion of rural and peri-urban areas had access to electricity.

He observed with sadness that the current 66 kv power supply which was adequate at the time of construction had negatively affected the provinces in question owing to among other reasons mining firms shunning to invest the areas while others ended up exporting unprocessed ore to the detriment of value addition and employment creation.

“It is unfortunate that the northern part of the country is under developed when it has huge potential for the mining industry which has so far not been realized due to insufficient and unreliable electricity supply.

“In addition, Northern Province harbours some of the best tourist attractions which have not been developed due to the same energy problems I have already alluded to,” he said.

Mr Yaluma observed that the project would go a long way in ensuring that there was increased access to electricity as per Government’s commitment, through ZESCO, to achieving the 50 per cent target set in the Vision 2030, which it was committed to realizing.

The Minister said there was need for electricity tariffs to reflect the actual cost of the service for them to sustain the service delivery of the power utility company and that provision of good and quality electricity supply to the four provinces needed not to be overmphaised.

Mr Yuxiao said it was a known fact that transmission lines were indispensible for economic development in any country as they played critical roles in all parts of the economy, citing mining, agriculture, education, health, tourism and manufacturing.

“Like blood vessels that carry oxygen to all parts of the human body, transmission lines deliver power to all sectors of an economy,” he said.

Mr Yuxiao said the most immediate and tangible benefits to be derived by the project was job creation of up to 3000, directly and indirectly. It was estimated that construction of the transmission lines would create 1000 direct and 2000 indirect jobs.

“After their completion, the power grid in Northern, Muchinga and Eastern Province will be greatly improved and upgraded and may even be extended to Tanzania and Malawi. Therefore, the power lines will not only deliver electricity to the power-thirsty remote areas and reduce poverty in Zambia, but will also likely bring earnings to Zambia through power export to the neighbouring countries,” he said.

He implored the Chinese firm engaged, Tebian Electric Apparatus (TBEA) Stock Company Limited, to implement the project with good quality and high speed coupled with abiding by Zambia’s relevant laws and regulations, employing as many local workers as possible as well as treating and paying them well.

TBEA Stock Company Limited vice president Li Bianqi who spoke through an interpreter said Zambia’s power usage had been rapidly increasing over the past decade and assured that the transmission lines would boost the various economic sectors.

Mr Li said his firm would exert its efforts using its high quality products coupled with engaging both skilled and non-skilled manpower in a bid to improve the living standards of the people in the operational areas.

ZESCO managing director Cyprian Chitundu said the two transmission lines in question would provide interconnection points for the Zambia-Tanzania and Malawi interconnectors, adding that it was envisaged that once completed, the interconnectors would enable for the improvement in the overall system stability as well as increasing regional electricity trade.

Northern Province Minister Freedom Sikazwe said he was hopeful that the groundbreaking ceremony marked the beginning of the resolution of the various electricity challenges the provinces were experiencing.

“The commencement of these two projects confirms our Government’s commitment to ensure that every Zambian regardless of where they stay have equal access to reliable and quality of electricity supply to improve their quality of life and standard of living,” he said.

Senior chief Mwamba, who Mr Chitundu among other senior company officials had paid a courtesy call on him at his palace, said commended the parties involved for the development and was hopeful that the project would benefit his subjects.

The aforementioned project’s total implementation cost would be broken down into two, with the Pensulo in Serenje to Kasama one costing US $168 million while US 166 million is for the implementation of the project from Pensulo to Chipata.

The project was necessitated by the signing of an Engineering Procurement and Construction (EPC) contract between ZESCO and TBEA Company Limited of China in September, 2010 and the two firms estimate to complete construction works in 30 months.

In the contract, ZESCO intends to construct a 330 kv high voltage transmission line emanating from Pensulo substation in Serenje to Kasama via Mpika and another 330 kv high voltage transmission line from Pensulo substation to Chipata via Msoro and extension of the existing Pensulo substation to accommodate the two transmission line bays.

A ZESCO study report based on Eastern, Northern, Luapula and Muchinga Provinces revealed that power demand was expected to increase in those areas arising from agricultural activities, mechanized tourism, mining explorations and operations.

24 COMMENTS

  1. Very use.less management ever at zesco.since Pathetic Front management came to zesco, there has been loadshedding without notice.Its like the fo0l incharge just presses the on/off button at will.

  2. The project will not reduce power outages. It doesnt create extra generation capacity. Politicians and their speeches. They are just dumb! No wonder you end up promising people what you cant deliver. Is everyone in PF this stupid? 

  3. These are the only fo0ls that make me miss RB.We never used to experience loadshedding as is experienced now during his time in office.I am now thinking of going solar.F0OLS.

  4. You fools you shud stop taking power in the morning what a silly government we voted for how do we eat in the morning and iron cloths when going for work, you get huge of monies and do lit job how many pipo are we zed still suffering like thus!!! residence of chimwemwe

  5. That is a good development. I hope by then copper mining in Mporokoso, Mwense, Chienge plus Manganese mining and Mansa batteries can get off. Luena farm block and sugar production in Kawambwa will take off. Mmmm, tea and sugar in Kawambwa. Further, Zampalm in Mpika will be processing oil. Beef production in Isoka, Chinsali would get Mbesuma ranch working. Chishinga ranch in Kawambwa can wake up …

  6. 5 star hotels can spring up at Kasaba bay, Mpulungu, Samfya, Mfuwe. Oil exploration in Samfya, Chama would be possible. We can talk of linking Tazara to Chipata-Mchinji railway line. Back to tourism, The Lumangwe, Kundabwika, Kabwelume falls on Kalungwishi can see investment. Talk of Kalambo, Chishimba, Mumbotuta, Ntumbachushi aah we are rich mwe. We ought to revive Lusenga National Park…

  7. It can be possible to set up cotton ginneries and peanut manufacturing plants in Chipata. More beef processing and milk production at Petauke. Improve management of Luangwa North and South. With all this, pedicle road will tarred then. And there is the Samfya beach for the taking. Mamama, Lunga, Chienge with immense potential for rice growing. Lunga can also double as a wildlife and biological sanctuary…

  8. We shall also need to build more universities. 2 at Chinsali in Muchinga. We shall need Bangweulu in Luapula and Bwezani Universities in Eastern Provinces.

  9. I dream that these things can come to pass. Hey, what about Ice plants and the abundant water at Mweru wa ntipa, Tanganyika, Mweru, Bangweulu, Kampolombo, Chila in Shiwang’andu, Luapula, Kalungwishi, Lufubu, Luongo, lushwishi and hundreds more?

  10. RATHER INVEST IN PROJECTS TO INCREASE ELECTRICAL GENERATING CAPACITY INSTEAD OF DIVERTING VALUABLE CASH TO ELECTRIFY AREAS WITH NO ECONOMIC ABILTY TO PAY FOR THE PROJECTS.

  11. Mr Chitundu how re u addressing the issue of minimum wage in your company of the unfairly paid casuals??

  12. Ba Liza naimwe, what comes first? People magically become economically able, then electricity can follow them? Or you take electricity to empower and create opportunities for economic boost through investment in various untapped areas? Muli bakopo x2. Why is it that you can’t even process mango juice in Mbereshi? Answer; power. A lot has to do with this commodity. What about Manganese, copper?

  13. Zambians can be ridiculous sometimes. The power shortage problem is not gonna end by one magic bullet in a matter of a month. Infact it requires a multi-faceted approach. It is known Kafue Gorge lower will have to be built with the Chinese. Ithezhi thezi is under construction, small ones like Kabompo, Mumbotuta, will be built with funds from Nigeria. These are capital projects which take even 5 years to finish.

  14. So, better be ready to live with load shedding for a long time. MMD woke up too late to start dealing with new power generation plants. In the meantime, PF is gonna bask in the glory once this project is done. If I check again, it says 2014 as finish date. Wonderbra, felicitations we shall shout in PF. By 2016 we shall be dancing all the way to the ballot box…kekekekeke, awe mwe. Pa Zambia…

  15. Needed to write you one little note in order to say thanks once again relating to the stunning tactics you have contributed above. This is so particularly generous with you to give openly what most people could have distributed for an electronic book to end up making some cash for their own end, chiefly now that you might have tried it in the event you desired. Those concepts additionally served to be a fantastic way to be sure that some people have the identical fervor much like my very own to see a lot more in respect of this condition. Certainly there are millions of more fun situations up front for many who read carefully your website.

  16. you might find distinctive varieties of sterling Louboutin clogs for example,that males Louboutin, hunter boots but also, Loafers flats for girls but also sterling Louboutin hunter boots, athletic shoes for males. at any rate from the straightforward simple fact that there does exist not on the same a terrific grant lifestyle improvements, sterling Louboutinto delivers force modification material. The route but also within light fixture criteria distinctive with each other fragile diddly greatest sterling clogs much many more marvelous convert Louboutin.

Comments are closed.

Read more

Local News

Discover more from Lusaka Times-Zambia's Leading Online News Site - LusakaTimes.com

Subscribe now to keep reading and get access to the full archive.

Continue reading