Copperbelt Province Minister Elisha Matambo has expressed disappointment at the slow progress made on the rehabilitation of selected township roads in Kitwe.
The media reports that Mr Matambo, who was accompanied by Kitwe District Commissioner Oncemore Ngonomo, Kitwe Mayor Mwaya Mpasa, and other stakeholders during an on-site inspection, called on the contractor to speed up the completion of the road works.
Mr Matambo said the contractor was expected to do about seventy percent of the work in seven months but only four percent has been covered.
The Minister has since called on the contractor, Nchifar Enterprises Limited, to appear before the provincial office and explain the cause of delays in making progress on the road works.
Mr Matambo, however, commended the contractor for the quality of work despite the delay.
The Minister also warned the contractor that the government will terminate the contract if there will be no change in completing the works.
Matambo unhappy with delays on Kitwe roads works