April 2008 ZANIS- Sinazongwe District Development Coordinating Committee (DDCC) has expressed disappointment at Zambia Electricity Supply Corporation’s (ZESCO) failure to complete power installation at Kariba South Primary School and four sites earmarked for Irrigation Schemes.
Sinazongwe District Commissioner Laiven Apuleni said ZESCO was frustrating government development projects in the district because money was paid in advance to light up the School but nothing has been done.
“I am not impressed with the operation of ZESCO in the district and in this era of information they are even failing to provide quotation and giving out bills at the district level but they have to go to Choma,” Mr Apuleni said.
Mr. Apuleni said poverty could not be addressed in the district if ZESCO fails to provide power to the four sites earmarked for irrigation Schemes.
He said it was difficult to understand why power has not been installed at the sites earmarked for irrigation schemes and at the School that was belt in Siansowa area when money was paid in advance.
The DC said government should have used the money on other activities if ZESCO had said they were not ready to do the work.
Sinazongwe District Planning officer Syamwiinga Siabbalo told the meeting that K50 million was paid to ZESCO in 2004 but nothing has been done.
He pointed out that the situation was hindering the provision of evening classes to reduce on illiteracy levels in the district.
Sinazongwe District Agriculture Coordinator Tundu kaonga said the African Development Bank (ADB) the financier of the Irrigation Schemes has expressed worry at ZESCO’s failure to complete the works on time.
Mr. Kaonga said the Bank has thrown the challenge on the local leadership to try and talk to ZESCO to ensure that power was installed at the sites before the contractor resumed work
He said Nzenga irrigation Scheme has been advertised and the contractor would be on the site before July.
Mr. Kaonga noted that the contractor would need power to complete some of his works within the stipulated time and it would be difficult if ZESCO fails to install power.
[ZANIS]